Due to typically having lower costs, this method is more often used than a newer one which drops the middle phase. For 10 points each:
[10h] Name this most common delivery method for planning and implementing construction projects. This method’s name consists of its three distinct phases.
ANSWER: design-bid-build [accept D/B/B]
[10m] The bidding process is completed by a party known by this term, who is then responsible for implementing the construction plan and hiring out other workers for specific tasks.
ANSWER: general contractor
[10e] Though the bidding process is typically based on cost, project owners may also consider the environmental impact and sustainability of the design, involving a branch of engineering described by this adjective.
ANSWER: green engineering