Due to typically having lower costs, this method is more often used than a newer one which drops the middle phase. For 10 points each:
[10h] Name this most common delivery method for planning and implementing construction projects. This method’s name consists of its three distinct phases.
ANSWER: design-bid-build [accept D/B/B]
[10m] The bidding process is completed by a party known by this term, who is then responsible for implementing the construction plan and hiring out other workers for specific tasks.
ANSWER: general contractor
[10e] Though the bidding process is typically based on cost, project owners may also consider the environmental impact and sustainability of the design, involving a branch of engineering described by this adjective.
ANSWER: green engineering
<TR>
Summary
2023 BHSU @ Berkeley | 03/18/2023 | Y | 3 | 13.33 | 67% | 67% | 0% |
2023 BHSU @ Maryland | 03/11/2023 | Y | 3 | 13.33 | 67% | 67% | 0% |
2023 BHSU @ Northwestern | 02/25/2023 | Y | 6 | 16.67 | 83% | 83% | 0% |
2023 BHSU @ Sheffield | 04/15/2023 | Y | 2 | 15.00 | 50% | 100% | 0% |
2023 BHSU @ Waterloo | 04/15/2023 | Y | 3 | 13.33 | 33% | 100% | 0% |
2023 BHSU @ Yale | 04/08/2023 | Y | 3 | 16.67 | 67% | 100% | 0% |
Data
Broken Imperial Nomads | Buzzers Karamazov | 0 | 10 | 0 | 10 |
Magisters Ludi | Oxford Hornets | 0 | 10 | 10 | 20 |